Hello Experts,
Using SAP ECC 6.0 for 15 months. We manufacture many different materials. Have not experienced this before. The first run of a new material did not create an inspection lot. None whatsoever and went directly to Unrestricted during goods receipt. Should have gone to QI.
Here's what I've checked.
Process Order
Goods Receipt indicates stock type = Quality inspection.
Points to a material recipe valid from 10/29/2014 with Recipe Group matching C203 for group number, production version and valid date
MM03
Related Inspection Type is defined and active. It also is clicked to post to inspection stock.
HOWEVER, I noticed the new material is designated with Revision A tag and became valid 11/21/2014 (23 days later). So if QM inspection setup lives in MM03, it's tied to material as Material X Rev A. Do you think this is related? If not what else should I consider? We made the material just days ago on 1/24/15
Also, how do I get an inspection lot created? QA01 doesn't have an option for 08. I don't think we configured it. Only 01 and 04 for stock relevant.
Thanks in advance. I looked in Frequently Asked Questions. Very Nice layout and content but didn't find this topic.