Dear experts ,
Need your advise on the following business requirement
Do let me know if this can be achieved , or is there any other custom way to approach.
We had a process where one material was existing in 4 different plants , and for each material/plant combination one QM autho
was assigned in material master. who was responsible for clearing the QC(Standard Process)
Now my business has merged all the four plants into one single plant from system prospective.
Here i have a requirement where business needs to maintain 4 QM autho of different plants for one material as plants are merged into
one single plant now (which is not possible in standard).
" I need to have different QM autho to be maintained for one single material , who all are responsible for clearing QC."
How to achieve this ..? At any point of time my business should be able to allocate the responsible for QC for respective materials'
Will be waiting for your valuable inputs experts.
Regards,
Daya