We are in process industry and currently all materials are batch managed but not HUM. Now we have plant in diff countries. In China we have oplant where storage location in WH managed and here process order rund of weeks or some time month.

 

So business do conformation on each day, some time couple of conformation on single day. Example each conformation pf 150 kg.

 

Currently when they do conformation, it goes to QI tab of an insp lot. Since inspection is running for weeks/month but business can't wait for week/month. So they post stock from QI to UNR and keep lot open because production is still running. In this scenario system create one more inspection lot for same batch which business doesn't like.

 

So question is what can we do so system does not create new lot and keep posting stock in open inspection lot? The reson for asking is production is running they and today's stock is good but not tomorrow's one. Can we achieve such kind of req using handling unit? Other than QM, what would be other challenges? We do transfer stock from one plant to another plant and in these plant we don't have such req, so i believe HUM won't support there. correct me if wrong.

 

This was the reason I asked below Q, but .