Experts,
I can not create Skip Lots using Source Inspection,
If I use Souce Inspection with ,
- Insp. plan type 51
- 0101 as inspection type at Quality view Material Master
- QI02 also with inspection type 0101, SI- no GR flagged
- Dynamic Rule at Lot Level
DMR,
- Stage 1 Normal Insp;ISt flagged;Insp.Qty.1; A=Stage2, R=Stage1
- Stage2 Skip flagged;Skip Qty 10; A=Stage2, R=Stage1
the dynamic rule is visible at lots created via QI07, showing the stage
Unfortunately the inspection stage does not change as I expected, it starts with starting stage e.g. 1 but won´t change to the next stage, independent if I use “usage decision” or “at lot leve”l at dynamic rule.
How should the “std” system interact, where should the skip status occur?
Thanks in advance
Jörg