Automatic calculation of sample size
Hi all, There is a requirement in my current project ,that for packaging goods when they procure suppose 1000 piece from vendor, for calculating sample they use the formula as square root of n+1....
View ArticleUnable to process QM material
Hi Friends We have case wherein one inspection lot was generated by Goods Receipt of 2 PO of different quantity with same batch. Auto UD completed for IL with only one Stock quantity and other...
View ArticleMethod did not associated to the Certificate
Please, I need some help. I've created a Inspection Method for a Master Inspection Characteristic at the QS31 and associated it at the QS23. This Master Inspection Characteristic already got one...
View Articlecalculation of sample size in Sample drawing procedure
Hi,I have created a sampling drawing procedure with following parameters.. Primary Samples: Fixed number 5 and size factor 2Pooled Samples : Fixed number 2 and size factor 2Reserve samples : Fixed...
View ArticleQM Active Movement Flag
Hi We have material A and want to control it at GR so that with one vendor inspection lots are created, whereas with a different vendor just QI stock is created. We were looking at 2 different movement...
View ArticleQM batches in-process inspection & goods receipt?
Gurus,we are working with partial lot creation & batches for in-process inspection.So, I created production order , entered 2 inspection points, then I assigned each inspection point a partial lot...
View ArticleInspection plan assignement for material
Hi Gurus, I have inspection plan group IN930004 valid from date 29.04.2011 & another group IN930207 created on 16.11.2011 & changed on 17.12.2013. I have an inspection lot created on...
View ArticleQ-Info record Option missing
Hello Gurus, I'm referring this to two different ERP systems.Quality info record option was available in one and does not appear in other.Can anybody through light on this issue ?1. 2. regardsRam
View ArticleLTIN & UD ICCO system status
Hello, I did search the part but couldn't find an explanation. This is related to system status in inspection lot screen i.e QA32. I have seen different system status after the UD completes as LTIN and...
View ArticleFormula field length
Hi all,Do someone know if its possible an easy to increase the length that you have inside, for example the inspection plan, to enter the formula for a calculated characteristic ?? (PLMKB-FORMEL2)...
View ArticleSend Email with Attached PDF in Quality notification
Hi Gurus, I have the following requirement: Need to send an email with an Adobe Form attached. I tried standard FM--> QM06_FM_TASK_SEND_PAPER_PDF /QM06_SEND_PAPER_STEP2_PDF combination but it won't...
View ArticleInspector Name on Result Recording Report.
Hi Gurus, I have a queire related to Inspector name.I required a name of a person on inspection report who do the result recording.I had taken theTable: -QAQEE & Field :-PRUEFER,Its works, But when...
View Articlei want to know the process for BIBO
dear experts i want to know the process for sap BIBO in net weaver7.3, and also i want to instal BIBO what we need? what are the pre requisites to install BIBO?, in DUMP what we have to mauntain? would...
View Articlehow can we determine the Usage Decision upon Material inspection...
Dear gurus, when we receive goods inspection lot is created.now when we put inspection result in inspection result If any critical Material Inspection Characteristic failed then user should not allow...
View ArticleMethod did not associated to the Certificate
Please, I need some help. I've created a Inspection Method for a Master Inspection Characteristic at the QS31 and associated it at the QS23. This Master Inspection Characteristic already got one...
View ArticleControlling the rejection
Hi Experts!Could u explain How to controlling rejections (FRDD & FRDS)? Thanks in advance.
View ArticleCheck Points / Control Parameters for the QM Module
Hi Experts, Since we are dealing with Business scenarios for the manufacturing industries, As per Standard every industry set for the process parameters,control parameters,work instructions,standard...
View ArticleAssigning an Inspection Specification
Hi,I need to assigning an Inspection specification to a material automatically. Regards,Ahmed
View ArticleControlling the Rejection
Hi Experts! Could you explain me about what is Controlling Rejection? Thanks in advance.
View ArticleOperation Master
We are working in a Project, where the client wants 1. To put the operation in the inspection plan and that automatically the master characteristics are created, for my understanding is kind of a...
View Article